Since six technicians working at the same rate completely work of one server in 10 hours.
Now, from 11:00 am to 5 pm total man hours = 6X6 = 36
From 5 pm to 6 pm total man hours = 7
From 6 pm to 7 pm total man hours = 8
From 7 pm to 8 pm total man hours = 9
and the total of this stands for 60 hours
Hence the work will be completed at 8 pm.